Project scheduling (RCPSP)

Sequence project activities under precedence and shared resource limits, choosing an execution mode for each, to finish as early as possible.

What it decides

For every job, the solver picks an execution mode and a delay. Start and end dates follow from those choices and from the precedence between jobs.

Minimal example

from optimaru import project_job_scheduling as pj
from optimaru.project_job_scheduling.models import (
    AllocationModel, ExecutionModeModel, JobModel, ProjectJobScheduleModel, ProjectModel,
    ResourceModel, ResourceRequirementModel,
)

def needs(amount):
    return [ResourceRequirementModel(resource_id="crew", requirement=amount)]

jobs = [
    JobModel(id="start", project_id="P1", job_type="SOURCE", successor_job_ids=["dig", "wire"],
             execution_modes=[ExecutionModeModel(id="start-0")]),
    JobModel(id="dig", project_id="P1", successor_job_ids=["end"], execution_modes=[
        ExecutionModeModel(id="dig-fast", duration=2, resource_requirements=needs(3)),
        ExecutionModeModel(id="dig-slow", duration=4, resource_requirements=needs(1)),
    ]),
    JobModel(id="wire", project_id="P1", successor_job_ids=["end"], execution_modes=[
        ExecutionModeModel(id="wire-0", duration=3, resource_requirements=needs(2)),
    ]),
    JobModel(id="end", project_id="P1", job_type="SINK",
             execution_modes=[ExecutionModeModel(id="end-0")]),
]
problem = ProjectJobScheduleModel(
    projects=[ProjectModel(id="P1", critical_path_duration=5)],
    resources=[ResourceModel(id="crew", capacity=3)],
    jobs=jobs,
    allocations=[AllocationModel(id=f"A-{job.id}", job_id=job.id) for job in jobs],
)

result = pj.solve(problem, time_limit_seconds=2.0, random_seed=42)
print(result.score_hard, result.score_medium, result.score_soft)
print([(a.job_id, a.execution_mode_id, a.start_date, a.end_date) for a in result.allocations])

The same use case as a Jupyter notebook, with charts and saved outputs: examples/project-job-scheduling.ipynb ↗

Input parameters

ProjectModel

Field Meaning
id required Project id. release_date Reference date for delay. It does not force the start. critical_path_duration Critical-path length. Delay is measured from release_date plus this.

ResourceModel

Field Meaning
id required Resource id. capacity required Per day if renewable, over the whole horizon if not. renewable True for capacity that recovers daily. project_id Owning project. None means a global resource, which must be renewable.

ExecutionModeModel

Field Meaning
id required Mode id. duration Days this mode takes. resource_requirements Resources it uses: a list of resource_id and requirement.

JobModel

Field Meaning
id required Job id. project_id required Owning project. job_type SOURCE, STANDARD or SINK. execution_modes At least one mode. SOURCE and SINK use one zero-duration mode. successor_job_ids Jobs that can start once this one ends.

AllocationModel

Field Meaning
id required Allocation id. job_id required The job. Allocations are 1:1 with jobs. pinned Keep this allocation's mode and delay. SOURCE and SINK are always pinned.

ProjectJobScheduleModel

Field Meaning
projects required Projects. resources required Resources. jobs required Jobs. allocations required One entry per job. delay_range_size Delays run from 0 up to this value, exclusive. 500 by default.

Solve parameters

What you pass to the solve call. Time limit, seed and parallel count are here.

Parameter Default Meaning
time_limit_seconds None Search budget in seconds, from 0 to 1e9. Left unset, it is the config's spent_limit_seconds, 30 by default.
random_seed None Seed for the search. Left unset, it is the config's value, 0 by default.
parallel_solver_count None Independent parallel starts. Each gets its own seed and the full budget, and the best result wins. Left unset, it is the config's value, 1 by default.
stop_at_first_feasible False Stop as soon as hard 0 is reached.
full_assert False Check every incremental score against a full recompute. Slow; for debugging.
on_new_best None Callback run on each new best solution. If it raises, the solve stops and raises the same exception.
config None A SolverConfig as the base configuration. Keyword arguments here override it for this solve only; the object you pass is not changed.
constraints None Which constraints to score, and how. Left unset, the defaults apply.
All search options (20)

Set these on a SolverConfig and pass it as config=.

Parameter Default Meaning
best_score_limit — Stop early once the best score reaches this value. By default it never fires.
change_move_weight 0.75 Relative share of change moves. 0 disables them.
full_assert False Check every incremental score against a full recompute. Slow; for debugging.
late_acceptance_size 0 Late-acceptance history length. 0 picks it from the instance size.
on_new_best None Callback run on each new best solution. If it raises, the solve stops and raises the same exception.
parallel_solver_count 1 Independent parallel starts, each with its own seed and the full budget. The best one wins.
random_seed 0 Seed for the search.
ruin_recreate True Run adaptive ruin-and-recreate kicks when the search stagnates.
ruin_recreate_max_ruin_count 60 Absolute cap on entities removed per kick.
ruin_recreate_max_ruin_fraction 0.3 Largest share of the solution one kick removes.
ruin_recreate_min_ruin_fraction 0.1 Smallest share of the solution one kick removes.
ruin_recreate_operator_decay 0.8 How fast operator weights adapt.
ruin_recreate_polish_steps 5000 Hill-climbing moves that polish each kick. Not counted against step_count_limit.
ruin_recreate_rewards [33.0, 9.0, 3.0, 0.0] Operator rewards for a new best, a better, an accepted and a rejected result.
ruin_recreate_unimproved_step_trigger 5000 Steps without a new best before a kick.
spent_limit_seconds 30.0 Time budget in seconds, from 0 to 1e9.
step_count_limit 0 Stop after this many steps. 0 means no limit.
swap_move_weight 0.25 Relative share of swap moves. 0 disables them.
unimproved_spent_limit_seconds 0.0 Stop after this many seconds without a new best. 0 means no limit.
unimproved_step_count_limit 0 Stop after this many steps without a new best. 0 means no limit.

What comes back

solve takes the model and returns the solved model.

AllocationModel

Field Meaning
execution_mode_id Chosen mode. delay Chosen delay. start_date Computed start day. end_date Computed end day.

ProjectJobScheduleModel

Field Meaning
score_hard Hard score. 0 means feasible. score_medium Medium score: total project delay, negated. score_soft Soft score: the latest finish, negated.

Constraints

Pick them by calling their classes from optimaru.project_job_scheduling.constraints, such as NonRenewableResourceCapacityCost(). Only what you pass is scored; pass nothing to keep the defaults. A list may name a constraint more than once, and each pick is scored on its own. Each one takes these parameters:

Parameter Default Meaning
weight None Multiplier on the constraint's cost, in units of the level in effect. Left unset, the default weight below applies. A constraint whose default weight is 0 is off until you give it a weight.
level None "hard", "medium" or "soft" moves the constraint onto that level, as do Level.HARD, Level.MEDIUM and Level.SOFT. Left unset, it keeps the level below. This use case has a medium level, and any constraint may move onto it.
exponent 1.0 Sign-preserving power on the cost, above 0, taken after offset. 2.0 squares it, so concentrated violations cost much more. It applies per unit, such as a vehicle or a day, or to the total of a constraint scored as one sum.
offset 0.0 Subtracted from the cost x before the exponent, per unit or total like the exponent. It is in the cost's own measure: seconds, minutes, a count and so on. Any finite number of either sign, keyword only. clip decides what happens below it.
clip True True makes offset a threshold: only the part beyond it counts, max(0, x - offset) ** exponent, so a cost at or below it adds nothing. False takes the literal (x - offset) ** exponent, sign kept: a unit below the offset counts negative, as a reward, even one whose cost is 0. On a level that counts toward hard, clip=False with a non-zero offset raises ValueError, since hard 0 must mean no violation. Keyword only.

A medium constraint weighs 1 in medium units by default. The search compares solutions on medium * 1e9 + soft, so medium outranks soft while the soft total stays below 1e9. With level, any constraint moves onto any of the three levels: level="medium" puts it on medium, and "hard" or "soft" takes a medium one off it. A weight counts in units of the level in effect.

This continues the minimal example above.

from optimaru.project_job_scheduling.constraints import (
    MakespanCost, ProjectDelayCost, RenewableResourceCapacityCost, get_constraints,
)

picked = get_constraints([RenewableResourceCapacityCost(), ProjectDelayCost(), MakespanCost(weight=2)])
custom = pj.solve(problem, time_limit_seconds=2.0, random_seed=42, constraints=picked)
print(custom.score_hard, custom.score_medium, custom.score_soft)
Name Level Default weight What it does
non_renewable_resource_capacity_cost Hard 1 Total demand on a non-renewable resource above its capacity.
renewable_resource_capacity_cost Hard 1 Per resource and day, demand above capacity.
project_delay_cost Medium 1 Days each project's SINK passes its critical-path end. Finishing early costs nothing.
makespan_cost Soft 1 Latest SINK end date, once for the whole schedule.

How constraints work →

Starting from an existing solution

This needs the latest release: pip install -U optimaru.

with_initial_solution(problem, solution) returns a copy of problem whose search starts from solution, the model a solve returned or that model as a JSON dict.

This continues the minimal example above.

seeded = pj.with_initial_solution(problem, result.model_dump(mode="json"))
again = pj.solve(seeded, time_limit_seconds=2.0, random_seed=43)
print(again.score_hard, again.score_medium, again.score_soft)
  • Allocations are matched by id.
  • A complete solution skips construction: the search starts exactly from it. A partial one keeps what it gives, and only the allocations it leaves out are constructed.
  • With time_limit_seconds=0 the solve stops at once, so a complete solution comes back as it went in. Use the time limit for this: step_count_limit = 0 means no limit.
  • Pinned allocations, which always include SOURCE and SINK, keep their value on problem, whatever the solution says.
  • ValueError is raised for an unknown id, for a mode that is not one of the job's, for a delay without a mode and for a delay outside the delay range.

Exceptions and limits

  • Give each project a SOURCE and a SINK job. Delay and makespan are read from SINK; without one, those terms score nothing and no error is raised.
  • Allocations must be 1:1 with jobs.
  • release_date is only a reference for delay. It does not hold a project back.